| Reference | BR/144/21/CLP |
| Status | PP Required |
| Proposal | Install a new paint booth into unit 1 Dickenson Place, facility. To allow this to happen we have been advised by the paint booth manufacturer 3 off (Ducts) flues will need to be put through the roof of unit 1, we therefore request information to advise us if planning permission is required for the installations of these roof flues (Ducts) or not. This building is categorised as a light industrial unit.
The requirements and dimensions for these flues (Ducts) has been defined by the manufacturer of the Spray booth as follows: -
Booth Exhaust = 1 No. ? 660mm - Ducting terminates 3m above the building ridge or highest point of building within 15m of opening
Booth Air Inlet = 1 No. ? 660mm - Ducting Terminate 1m from roof opening (or via wall of building)
Paint Mixing Room
1 No. ? 150mm = Ducting terminates 3m above roof opening |
| Location | Unit 1 Dickinson Place Bognor Regis PO22 9QU |
| Parish | Bognor Regis |
| Case Officer | Miss K Welch |
| Received | 18-05-21 |
| Validated | 27-05-21 |
| Decision By | 22-07-21 |
| Decided | 15-07-21 |
| Applicant | Mr M Mew Unit 2 Dickinson Place South Bersted Business Park Bognor Regis PO22 9QL |
| Agent | Mr M Mew Unit 2, Dickinson Place, South Bersted Business Park Bognor Regis PO22 9QL |