Proposal | Non-material amendment following the grant of CM/16/18/PL (APP/C3810/W/19/3227374) for:
- The raising of the ground and finished floor level of the approved building by 300mm;
- Installation of air source heat pumps within an associated enclosure together with a new electricity substation building;
- Incorporation of the approved highway works (as shown in the proposed highway improvements plan dwg no. 025 Rev. P7) into the proposed site plan in the interests of consistency between approved plans and drawings;
- Inclusion of proposed new hard and soft landscaping details within the amended proposed site plan together with an associated amendment to condition 6 of the planning permission so that it states:
The approved scheme of hard and soft landscaping as shown in drawing no. APL003 Rev. A shall be fully carried out in the first planting and seeding season following the first occupation of the building or the substantial completion of the development, whichever is the sooner. Any trees or plants which, within a period of five years from the completion of development, die, are removed or become seriously damaged or diseased, shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation. |